Ring beam complete. Structure matches agreed phase plan. No structural failures found, but 1 technical note requires your attention below.
Foundation
Rebar Detail
Formwork
Concrete Pour
Wide Overview
East Elevation
North Elevation
Materials Store
Site Activity
9 of 12 photos shown โข All GPS-tagged โข Timestamped โข View location โ
The concrete beam above the east window has a minor sag (~5mm). Not structural, but recommend a professional check before loading roof trusses.
| Material | Quantity | Status | Notes |
|---|---|---|---|
| PPC Cement | 8 bags | Present | Bags intact, under waterproof cover |
| River Sand | ~3 tonnes | Present | Near northern boundary |
| Quarry Stone | ~2 tonnes | Present | Adequate for current phase |
| Roof Trusses | 0 | Not Yet | Expected for next phase |
Mortar joints are consistent and evenly spaced. Brickwork appears plumb and straight. Ring beam is continuous with visible rebar. General impression: quality work by an experienced team.
Ring beam phase is complete as claimed by the builder. This is consistent with what you would expect after 6 weeks of active work from DPC stage.
Before roofing can begin, roof trusses need to be delivered and the ring beam must cure for at least 7 days (poured June 14). Builder should not load trusses before June 21 at earliest.
This assessment reflects observable conditions only. It is not an engineering inspection or structural certification.
๐ Know someone building from abroad?
Their first verification is free with your referral.
SiteWatch reports document observable conditions at the time of visit. They are not engineering inspections or structural certifications.
Report ID: SW-2026-0847 โข Verifier: Farai Mapfumo โข SiteWatch Zimbabwe