ON TRACK ยท 1 Note

Ring beam complete. Structure matches agreed phase plan. No structural failures found, but 1 technical note requires your attention below.

๐Ÿ“ Stand 1234, Borrowdale, Harare ๐Ÿ“… 18 June 2026 ๐Ÿ—๏ธ Ring Beam Phase
Build Progress โ€” Ring Beam โ†’ next: Roof 45%
๐Ÿ“ Proof of Presence
๐Ÿ“ -17.7654ยฐS, 31.0504ยฐE โ€” Tap to view on Google Maps
GPS Accuracy
ยฑ3.2m โœ“
Geofence Match
Within 12m of stand โœ“
Time on Site
10:14 AM โ€“ 10:58 AM (44 min)
๐Ÿ“ธ Site Photography
Foundation Foundation 10:18 AM ยท ยฑ3m
Rebar detail Rebar Detail 10:22 AM ยท ยฑ4m
Formwork Formwork 10:28 AM ยท ยฑ3m
Concrete pour Concrete Pour 10:35 AM ยท ยฑ5m
Site overview Wide Overview 10:15 AM ยท ยฑ3m
East elevation East Elevation 10:40 AM ยท ยฑ3m
North elevation North Elevation 10:44 AM ยท ยฑ4m
Materials Materials Store 10:48 AM ยท ยฑ3m
Workers on site Site Activity 10:52 AM ยท ยฑ3m

9 of 12 photos shown โ€ข All GPS-tagged โ€ข Timestamped โ€ข View location โ†—

๐Ÿ“‹ Ring Beam Phase Checklist
โœ“
Foundation level and plumb
โœ“
DPC membrane intact
โœ“
Walls plumb at window level
โš ๏ธ
Lintels correctly placed

The concrete beam above the east window has a minor sag (~5mm). Not structural, but recommend a professional check before loading roof trusses.

โœ“
Ring beam continuous around building
โœ“
Steel rebar visible in beam (Y12 at 200mm)
โœ“
Corners properly tied and lapped
โ—‹
Roof structure installed (next phase)
โ—‹
Roofing sheets fitted (next phase)
๐Ÿงฑ Materials On Site
MaterialQuantityStatusNotes
PPC Cement8 bagsPresentBags intact, under waterproof cover
River Sand~3 tonnesPresentNear northern boundary
Quarry Stone~2 tonnesPresentAdequate for current phase
Roof Trusses0Not YetExpected for next phase
Summary: Materials on site are sufficient for the current phase. Roof trusses not needed until ring beam has cured (est. June 21).
๐Ÿ—๏ธ Verifier's Assessment

Overall Workmanship

Mortar joints are consistent and evenly spaced. Brickwork appears plumb and straight. Ring beam is continuous with visible rebar. General impression: quality work by an experienced team.

Progress vs. Expectation

Ring beam phase is complete as claimed by the builder. This is consistent with what you would expect after 6 weeks of active work from DPC stage.

Next Phase Advisory

Before roofing can begin, roof trusses need to be delivered and the ring beam must cure for at least 7 days (poured June 14). Builder should not load trusses before June 21 at earliest.

This assessment reflects observable conditions only. It is not an engineering inspection or structural certification.

๐Ÿ’ก What To Do Next
Book Next Visit โ€” $35
๐Ÿ—‚๏ธ Verification History
18 June 2026
Ring Beam Complete
โœ“ On Track ยท 1 note
2 June 2026
Window Level
โœ“ On Track
15 May 2026
DPC Complete
โœ“ On Track

๐ŸŽ Know someone building from abroad?
Their first verification is free with your referral.

SiteWatch reports document observable conditions at the time of visit. They are not engineering inspections or structural certifications.
Report ID: SW-2026-0847 โ€ข Verifier: Farai Mapfumo โ€ข SiteWatch Zimbabwe